Changes to the Referral Process for Development Applications
Since 1 July 2026, the Development Coordination Authority (DCA) has become the primary body to which development applications (DAs) that require consultation, concurrence, or approval from other public authorities must be referred.
Before the new framework, there were more than 800 provisions across NSW planning legislation and environmental planning instruments that required a referral to an external public authority. The new DCA framework consolidates those requirements so that almost all referrals (including for consultation, concurrence or approval) are simply made directly to the DCA, who acts as the representative for other agencies.
However, while there has been much discussion about the introduction of the DCA itself, less attention has been given to other significant changes to the referral process given effect by the Environmental Planning and Assessment Amendment (Planning Systems Reforms) Act 2025, such as those set out below.
Pre-referral check
The insertion of s 42 in the Environmental Planning and Assessment Regulation 2021 (EPA Reg) creates a mandatory “pre-referral check” process, where the consent authority must determine what referrals it thinks are necessary for the DA and give that list to the DCA.
The consent authority must give the DCA 2 days to respond to the pre-referral check before formally referring the DA to the DCA.
The DCA guidance materials state that the key purpose of this check is to reduce “unnecessary” referrals. However, it is not clear what would happen where there is a disagreement between the DCA and a consent authority about what referrals are required.
It is notable that a consent authority is not bound by the DCA’s response to a pre-referral check and therefore it seems to us that the consent authority could still seek to refer a DA to a particular agency even if the DCA has advised that there is no requirement for such a referral.
Identifying integrated development
Integrated development has generally been treated as an “opt-in” scheme (see Maule v Liporoni [2002] NSWLEC 25). That is, an applicant could elect whether to have its DA dealt with as integrated development.
The new DCA framework appears to place the decision more squarely in the hands of the consent authority. As part of the pre-referral check process, the consent authority must consider whether a DA requires an integrated development approval.
That is consistent with the recent decision of the Court in Friends of Bucketty Incorporated v Buckettys Brewery Pty Ltd [2026] NSWLEC 118, where the Court found that whether or not development is integrated is a jurisdictional fact and not a discretionary matter for an applicant to elect. You can read our article about that case here.
The NSW Planning Portal has also been updated so that applicants are more clearly asked at the pre-lodgement stage whether a concurrence or referral is required for their DA. Where an applicant selects “no” or “unsure”, the Portal expressly warns that a DA may still require review by another agency and that additional approvals may be required before construction commences.
Modification applications
The reforms also change when a modification application must be referred.
A modification will generally only need to be referred where:
- the modification triggers a referral that would have been required if the development, as modified, had been the subject of a new DA, or
- the modification affects a condition or requirement imposed by, or based on, the response to an earlier referral: s4.44 – s4.45 State Environmental Planning Policy (Planning Systems) 2021.
In relation to the latter scenario, the scope of phrase “affects a condition or requirement” is not entirely clear. It is likely to capture not only proposed modifications to conditions imposed by an agency, but also to design changes which relate to or affect the substance of those conditions.
Prescribed timelines for the referral process
Under the new DCA framework, the consent authority must refer the application to the DCA as follows:
- The consent authority issues a pre-referral check to the DCA.
- The consent authority refers a DA to the DCA within 14 days of the DA being lodged, but not sooner than 2 days after the pre-referral check being submitted: s43 EPA Reg.
- The DCA may request further information for its assessment, which will stop the clock for the referral period: s44(4), s46 EPA Reg.
- The DCA must provide its response to the referral within 28 days: s44(1) EPA Reg.
- If no response received in 28 days, consent authority can determine the application: s4.13 and s4.47 Environmental Planning and Assessment Act 1979.
Proceedings in the Land and Environment Court
We note that the reforms provide no guidance as to the process for referring DAs as required during the course of proceedings in the Land and Environment Court. It remains to be seen whether the DCA would take on any role in that process or whether parties would be dealing directly with the relevant agency.
Section 8.12 of the EPA Act has not been amended, and therefore it seems that a consent authority must still give notice of proceedings directly to the relevant approval bodies (and not the DCA), although how this operates in practice remains to be seen.
Implications
The success of the DCA will ultimately depend on whether the new system produces faster and more predictable responses without diminishing the quality of technical input from specialist agencies. It seems to us that there are a number of areas of doubt in relation to the operation of the new framework, as discussed above, which may result in a period of uncertainty before any efficiency gains are realised.
The DCA has published a new State Referral Provisions document, intended to operate as a practical guide to the new referral framework. It identifies the matters considered by the DCA and other bodies when responding to referrals and is likely to become an important reference point for councils and planning consultants, and can be accessed here: State Referral Provisions.
For further information, refer to the DCA’s frequently asked questions page and the 1 July 2026 release notes.
In you have any questions about this article, leave a comment below or contact Dimitrious Havadjia.

Leave a comment
in focus comments policy
LTL welcomes your feedback and comments on our posts. all comments, however, will be moderated and we reserve the right not to publish any comment for any reason.
LTL in focus is primarily designed for public sector and development professionals dealing in the fields of planning, environment and government. you may, therefore, wish to consult your organisation’s social media policy before you post any comments. it should go without saying that we expect all comments to maintain a level of respect and professional courtesy.
Please note we are unable to provide specific legal advice via these comments. If you wish to engage us to provide legal advice on a matter, please contact our office directly.
In making a comment you are required to provide your email address, this will not be published on the site. if the moderator chooses to publish your comment, the name you provide will be published with your comment – it is your choice whether you provide your full name or just your first name. if you provide your full name, we may seek to verify your identity prior to publication of your first comment. If you wish your comment to be directed only to the author or moderator please make that clear – marking it NFP or Not For Publication is the easiest way. thank you for your support and happy reading – matthew mcnamara, ceo.