Posted on October 13, 2026 by Megan Hawley

Integrated Development Process is Mandatory

In a recent decision, the Land and Environment has re-considered the question of whether a consent authority is required to treat a development application as proposing ‘integrated development’, even if the applicant does not indicate on the development application form that the development is integrated development.

Background

‘Integrated development’ is defined in s4.46 of the Environmental Planning and Assessment Act 1979 (EPA Act) as ‘…development (not being State significant development or complying development) that…requires development consent and one or more of the following approvals…’ . There then follows a list of various approvals under other legislation that may be required for development to be carried out.

Back in 2002, in the case of Maule v Liporoni [2002] NSWLEC 25, Lloyd J of the Land & Environment Court said that the integrated development provisions of the EPA Act were beneficial and facultative, and it was up to the applicant for development consent to elect whether a development application was to be processed as being for integrated development. In that case, the applicant had not ticked the box on the DA form to indicate the development was integrated development , and  it was held not to be an error for the consent authority to treat the application as not being for integrated development.

That decision has been treated with caution for some time, but has not previously been overturned.

In the recent decision, Friends of Bucketty Incorporated (Applicant) commenced Class 4 judicial review proceedings challenging a consent granted by Cessnock City Council including on the basis that the Council failed to treat the proposal as integrated development. This raised two questions. First, whether one of the approvals under s4.46 of the EPA Act was required (in the case the relevant approval was a controlled activity approval under s91 of the Water Management Act 2000), and second, if the controlled activity approval was required, whether that meant the Council was in error by not treating the development as integrated development, which turned on whether the integrated development provisions are mandatory or procedures that an applicant may elect to pursue.

Decision

The Court concluded that whether a proposal is “integrated development” under s 4.46 of the EPA Act is a jurisdictional fact. The Court may therefore have regard to additional evidence not before the council when determining if one of the approvals listed in s4.46 is required, and the development is integrated development.

The Court noted in coming to that conclusion that the provisions in Division 4.8 of the EPA Act in respect of integrated development are not expressed to be based on a discretion or the opinion of the consent authority. The Court therefore concluded that the provisions are mandatory provisions and do not provide for a procedure which an applicant may ‘elect’ to pursue.

The Court also noted that the beneficial and facultative purpose of Div 4.8 of the EPA Act, as disclosed by the second-reading speech when it was introduced into the EPA Act,  was is not confined to the convenience of applicants. Div 4.8 was enacted to reduce delay, duplication, inconsistency and environmental cost by bringing multiple approvals into a single coordinated process for the benefit of the community and the environment. That purpose would be frustrated if an applicant could elect out of the regime, or a council could simply ignore it, whenever a development objectively required a listed approval.

In summary, the integrated development process is mandatory where a development requires development consent, is not SSD or complying development, and requires one of the approvals listed in s446 of the EPA Act.

Implications

Applicants need to carefully consider whether their developments are properly considered to be integrated development, and cannot assume that if they do not tick the box to have their DA dealt with under the integrated development process, their consent will be valid, and they can later obtain any additional approvals required. Any consent granted which has not followed the integrated development process, if such an approval is required, could be subject to challenge.

Councils and other consent authorities should also carefully review development applications they receive to determine what other approvals may be required, and seek further information from applicants in the event of uncertainty to avoid challenges. Consent authorities cannot rely on the applicants indication on a DA form.

The full text of the Land and Environment Court’s judgment can be found here: Friends of Bucketty Incorporated v Buckettys Brewery Pty Ltd [2026] NSWLEC 118.